Installation of anti-pid04-3 in an 80 kW PV park in Melampes
After measurements made with a thermal camera and I-V open circuit measurements, a reduced system performance was observed by the PID (Potential Induced Degradation) in the 80 kw PV installation.
For this reason, ANTI-PID04-3 anti-PID countermeasures were installed in order to restore the PV system to its original performance in a period of approximately 3 to 6 months.
Park Details:
- PV panel Yingli solar 260W
- Inverter SMA 15kW
- Stable Bases